| 2026-08-24 |
BE-202605856 |
Low voltage |
fire alarm modifications |
— |
| 2026-08-24 |
BE-202605899 |
Low voltage |
Low Voltage data Cabling |
— |
| 2026-08-14 |
BM-202603886 |
HVAC |
Lobby and Restroom renovations |
— |
| 2026-07-22 |
BE-202604985 |
Electrical |
New circuitry installed for security desk & coffee bar, outlets. lighting and lighting controls. |
— |
| 2026-07-21 |
BP-202602916 |
HVAC |
Install coffee bar in lobby and wash sink in closet. Connect grease waste to new grease interceptor in mechani |
— |
| 2026-07-09 |
BP-202602755 |
Addition |
AFPS SHALL ADD/RELOCATE A TOTAL OF 48 SPRINKLER HEADS IN ORDER TO PROVIDE ADEQUATE COVERAGE PER NFPA 13, 2022. |
— |
| 2026-06-29 |
BM-202602955 |
HVAC |
Including, but not limited to duct alterations and installation of new terminal units and air distribution. |
— |
| 2026-06-29 |
BP-202602633 |
Plumbing |
Including, but not limited to installation of new plumbing and fixtures. |
— |
| 2026-06-25 |
BE-202604437 |
Low voltage |
Low Voltage data Cabling |
— |
| 2026-06-25 |
BE-202604434 |
Electrical |
Tenat SpaceLights, Switches & Receptacles |
— |
| 2026-06-10 |
BP-202602343 |
Addition |
CENTURY TO ADD AND RELOCATE OFF THE EXISTING FIRE SPRINKLER SYSTEM PER NFPA 13. |
— |
| 2026-06-09 |
BP-202602330 |
Remodel |
adding 1 sprinkler head |
— |
| 2026-06-04 |
BM-202602493 |
HVAC |
new low pressure duct, new/relocated supply and return grills, insulation |
— |
| 2026-05-27 |
BE-202603631 |
Electrical |
Lights & Switches |
— |
| 2026-04-29 |
BB-202603850 |
Demolition |
DEMO PACKAGE TO PREP FOR NEW OFFICE SPACE. |
— |
| 2026-04-29 |
BB-202603849 |
Commercial fit-out |
New tenant is taking over an existing suite 700 at The Pinnacle building located at the address noted. The sui |
— |
| 2026-04-28 |
BE-202602860 |
Low voltage |
10th floor - Update 5 Conference rooms with new furniture & technology. Build out 2 team rooms with new furnit |
— |
| 2026-04-21 |
BE-202602650 |
Low voltage |
2nd Floor(1) BPS10A 10 Amp Booster Power Supply(2) 12V7AH Battery(11) EG4VWF Wall Mounted Strobe(1) EG4SVWF Wa |
— |
| 2026-04-20 |
BE-202602620 |
Low voltage |
2nd, 4th & 10th Floor Renovation work to the access control and cctv devices. Reference device placement from |
— |
| 2026-03-26 |
BE-202602047 |
Electrical |
Tenant SpaceLights, Switches & Receptacles |
— |
| 2026-03-26 |
BE-202602049 |
Low voltage |
Fire Alarm Modifications |
— |
| 2026-03-23 |
BP-202601167 |
Addition |
add and relocate sprinkler heads to code |
— |
| 2026-03-19 |
BE-202601870 |
Low voltage |
Install independent white noise systems on each level. |
— |
| 2026-03-13 |
BB-202602251 |
Plumbing |
Second generation white boxed suite within a multi-story office building. The project scopeconsists of: Demoli |
— |
| 2026-03-11 |
BE-202601668 |
Low voltage |
175 Drops and 1 MDF |
— |
| 2026-03-10 |
BP-202600972 |
Addition |
add and relocate sprinkler heads to code |
— |
| 2026-03-03 |
BE-202601370 |
Low voltage |
Fire Alarm Modifications |
— |
| 2026-03-03 |
BE-202601369 |
Low voltage |
Fire alarm Modifications |
— |
| 2026-03-02 |
BP-202600820 |
Plumbing |
Install 2 urinals, 6 toilets, 6 lavatory, 1 drinking fountain |
— |
| 2026-03-02 |
BM-202600970 |
HVAC |
new low pressure duct, new/relocated supply and return grills, insulation |
— |