| 2026-08-25 |
BP-202603376 |
Plumbing |
Install sink and faucets x 2, water heaters x 2, dishwasher x 1 |
— |
| 2026-08-25 |
BM-202604117 |
HVAC |
new low pressure duct, new/relocated supply and return grills, insulation |
— |
| 2026-08-23 |
BE-202605842 |
Low voltage |
Add network lines |
— |
| 2026-08-20 |
BE-202605787 |
Electrical |
Electrical Buildout of Existing Suite 200 |
— |
| 2026-08-04 |
BP-202603079 |
Plumbing |
Install of 1 sink, 1 water heater |
— |
| 2026-08-04 |
BM-202603672 |
HVAC |
new low pressure duct, new/relocated supply and return grills, insulation |
— |
| 2026-07-22 |
BE-202605002 |
Low voltage |
(1) ELSTW LED Strobe White Wall 24V 15/30/75/110/135/185CD(1)HPF-PS10 Power Supply Remote Charger Power Supply |
— |
| 2026-07-20 |
BB-202606291 |
Electrical |
TENANT BUILD OUT IN SECOND GENERATION SPACE. THE RENOVATION INCLUDES MINOR DEMOLITION, WITH SOME NEW WALLS, DO |
— |
| 2026-07-17 |
BE-202604899 |
Electrical |
Electrical Second Generation Build Out |
— |
| 2026-07-17 |
BP-202602885 |
Plumbing |
Including, but not limited to installation of new plumbing and fixtures. |
— |
| 2026-07-17 |
BM-202603307 |
HVAC |
Including, but not limited to duct alterations and installation of new terminal units and air distribution. |
— |
| 2026-07-14 |
BE-202604808 |
Low voltage |
Add / relocate Speaker strobes per the plans. And add one smoke detector. |
— |
| 2026-07-09 |
BE-202604717 |
Electrical |
Commercial interior build out with new lighting & power outlets. Contacts: Alfred Belisario, Project Manager # |
— |
| 2026-07-09 |
BP-202602753 |
Addition |
CENTURY TO ADD AND RELOCATE OFF EXISTING SYSTEM IN ORDER TO PROVIDE PROPER PROTECTION PER NFPA 13 |
— |
| 2026-07-01 |
BB-202605768 |
Commercial fit-out |
*New Tenant*PROPOSED BUSINESS INTERIOR BUILDOUT OF AN EXISTING BUSINESS SUITE INAN EXISTING OFFICE BUILDING. E |
— |
| 2026-06-23 |
BB-202605462 |
HVAC |
DEMOLITION SCOPE OF WORK FOR AN INTERIOR BUILDOUT OF AN EXISTING BUSINESS SUITE IN AN EXISTING OFFICE BUILDING |
— |
| 2026-06-09 |
BP-202602322 |
Addition |
CFP is contracted to add and relocate sprinklers off of existing wet system to meet NFPA 13 requirements |
— |
| 2026-05-22 |
BB-202604539 |
HVAC |
THE RENOVATION INCLUDES MINOR DEMOLITION, SEVERAL NEW WALLS, LIGHTING, MILLWORK AND FINISHES. EXISTING EXITS A |
— |
| 2026-05-19 |
BB-202604422 |
Electrical |
TENANT BUILD OUT IN SECOND GENERATION SPACE. CONSTRUCTION INCLUDES MINOR DEMOLITION AND SEVERAL NEW WALLS. EXI |
— |
| 2026-04-09 |
BP-202601425 |
Addition |
CENTURY TO ADD AND RELOCATE OFF THE EXISTING FIRE SPRINKLER SYSTEM PER NFPA 13. |
— |
| 2026-03-30 |
BS-202600246 |
Sign |
building monument |
— |
| 2026-03-03 |
BE-202601384 |
Low voltage |
Low Voltage Cable Installation |
— |